Was just in the Black Hills the other day and thought I would pass along some construction updates in case you are planning things:
- There are multiple areas of single lane closures for re-surfacing and bridge repairs ranging from 14 - 18 miles long between Chamberlain and Rapid City on I90
- There is another traffic adjustment/lane closure on I90 as you approach Rapid from the East
- 385 out of Lead heading south has a MAJOR repair taking place and you have to run on gravel for about a mile or so. This affects both sides of the road so it will likely be a major source of slowdowns/stoppages during the rally
- Nemo Road has a bridge out somewhere north of Norris Creek Rd. so you likely won't be able to ride the entire stretch of road.